A direct cost is a cost you can tie to one specific project, contract or grant, like the pay and travel of a crew working that job, and charge straight to it.

Not to be confused with: an indirect cost, which is shared across several projects and spread among them, like rent or the accounting department.

Updated November 18, 2026 by Engine Editorial

## What is a direct cost?

A direct cost belongs to one job. This cheat sheet covers how to tell direct from indirect, where travel fits and what federal contract rules ask you to document before you charge a trip.

### How to think about it

- **It's traceable.** Federal rules call a cost direct when it can be identified with a particular cost objective, such as an award or project, or assigned to it relatively easily with a high degree of accuracy.
- **Travel can be direct.** FEMA lists travel of direct labor employees as a typical direct cost, next to their pay, their fringe benefits and materials bought for a specific award.
- **The purpose decides, not the type.** Federal grant rules say there is no universal rule for classifying costs. A cost may be direct for one function and indirect for another.
- **Pick once, then stay consistent.** Costs incurred for the same purpose in like circumstances must be treated consistently as direct or indirect, so an award isn't charged twice.

### The math

Total direct costs = direct labor + other direct costs.

NIH's example has $300,000 in direct labor and $100,000 in other direct costs, so $300,000 + $100,000 = $400,000

_Illustrative example from NIH's indirect cost rate guide. Which costs count as direct depends on what each one was for._

### Before you charge travel to a federal contract

- **Document the trip.** FAR allows travel costs only when the date and place of the expenses, the purpose of the trip and the traveler's name and title or relationship to the contractor are documented.
- **Stay inside per diem.** Lodging, meals and incidentals are reasonable and allowable only up to the maximum per diem rates in effect at the time of travel, outside special situations.
- **Keep receipts over $75.** When special situations justify actual costs above per diem, each expenditure of $75 or more needs a receipt.
- **Watch the airfare.** Airfare above the lowest priced fare available during normal business hours is unallowable unless a listed exception applies and is documented.

## Direct cost vs. indirect cost

| | Direct cost | Indirect cost |
| --- | --- | --- |
| What it is | Identified with one cost objective, such as a contract, award or project | Incurred for a common purpose that benefits more than one cost objective |
| Examples | Pay and fringe benefits of employees working on the award, their travel, materials bought for it | Rent, utilities, officers' salaries, accounting and personnel department costs |
| How it's charged | Charged directly to the contract or award | Grouped into pools and spread across projects with an indirect cost rate |

## How it works on Engine

With [Engine travel reporting](https://engine.com/features/travel-reporting-analytics), company-defined fields such as department, project, job code and cost center add the business context for filtering, so finance can pull a filtered report instead of assembling scattered records. Engine recommends choosing consistent cost fields before bookings begin. Trips booked outside Engine aren't automatically included.

## Tag every trip to its project

Capture project, job code and cost center fields on Engine bookings and filter travel spend by them. Free to use.

[Get started](https://engine.com/sign-up)

## Questions

### What is direct cost and examples?

A direct cost is one you can tie to a specific project, contract or award. FEMA's examples are pay and fringe benefits for employees working on the award, travel of those employees, and materials and supplies bought for that award.

### What is a direct and indirect cost?

A direct cost belongs to one cost objective and is charged to it directly. An indirect cost serves more than one and can't readily be assigned to any of them without disproportionate effort, like rent, utilities or the accounting department.

### What is the formula for direct cost?

Add up the costs traceable to the work. In NIH's example, $300,000 in direct labor plus $100,000 in other direct costs gives $400,000 in total direct costs.

### Is business travel a direct or indirect cost?

It depends on the trip. FEMA lists travel of employees working directly on an award as a direct cost, and federal rules say no cost type is automatically direct or indirect, so what the trip was for decides.

### Can a small direct cost be treated as indirect?

Yes. Under FAR 31.202, a contractor may treat a direct cost of a minor dollar amount as indirect, as long as the treatment is applied consistently and produces substantially the same results.

### How do you track travel as a direct cost?

Capture the project when the trip is booked. On Engine, company fields such as project, job code and cost center can be captured, and finance can filter travel spend by them.

## Go deeper

- [Indirect cost](https://engine.com/glossary/indirect-cost)
- [Cost allocation](https://engine.com/glossary/cost-allocation)
- [Cost center](https://engine.com/glossary/cost-center)
- [General ledger](https://engine.com/glossary/general-ledger)
- [Engine travel reporting and analytics](https://engine.com/features/travel-reporting-analytics)

## Sources

1. Electronic Code of Federal Regulations, "2 CFR 200.413 Direct costs," https://www.ecfr.gov/current/title-2/chapter-II/part-200/subpart-E/section-200.413, accessed November 18, 2026.
2. Electronic Code of Federal Regulations, "2 CFR 200.412 Classification of costs," https://www.ecfr.gov/current/title-2/section-200.412, accessed November 18, 2026.
3. Federal Acquisition Regulation (Acquisition.gov), "31.202 Direct costs," https://www.acquisition.gov/far/31.202, accessed November 18, 2026.
4. Federal Acquisition Regulation (Acquisition.gov), "31.205-46 Travel costs," https://www.acquisition.gov/far/31.205-46, accessed November 18, 2026.
5. Federal Emergency Management Agency, "What are Direct and Indirect Costs?," https://www.fema.gov/node/what-are-direct-and-indirect-costs, accessed November 18, 2026.
6. National Institutes of Health, "Indirect Cost: Definition and Example," https://oamp.od.nih.gov/division-of-financial-advisory-services/indirect-cost-branch/indirect-cost-submission/indirect-cost-definition-and-example, accessed November 18, 2026.
7. Engine, "Travel Reporting and Analytics," https://engine.com/features/travel-reporting-analytics, accessed November 18, 2026.